% of planned shelter site inspections verifying covered living space and construction safety completed on schedule

Definition & calculation

Numerator: Number of planned shelter site/technical inspections (covering covered living space per person and construction safety) completed by their scheduled date

Denominator: Total number of shelter site/technical inspections planned in the workplan for the reporting period

Divide the number of scheduled shelter inspections completed on time by the total number planned in the workplan for the period, multiplied by 100.

Formula: (Numerator ÷ Denominator) × 100

Means of verification

Construction supervision workplan and inspection tracker

Interpretation

Direction: Higher is better

Typical reporting frequency: Per activity cycle / continuous

Guidance & common pitfalls

A process/timeliness measure of supervision and quality assurance; on-schedule inspections check minimum covered floor area per person and structural safety, but completing an inspection does not by itself indicate that standards were met.

This library is a curated reference to adapt, aligned generically with recognised humanitarian frameworks (Sphere, cluster registries, IASC, CHS and others). It is not an official indicator registry — always use the exact indicator definitions your donor or cluster requires.

Indicator library

Turn these indicators into a live logframe.

Build your logframe, set targets, disaggregate results and generate donor reports — all in one connected system. See how Humanitarian Ops handles MEAL end to end. We usually reply within 24 hours.

Explore MEAL & reporting